2013年8月20日星期二

National standards for outdoor fitness equipment installation and site requirements

Given that most dealers or customers horizontal bar, parallel bars, ladders, uneven bars, swings and other outdoor fitness equipment installation is not in accordance with the "fitness equipment outdoor fitness equipment General requirements for safety" GB19272-2003 requests. To ensure the installation site and installation process in line with the national standard, now the national standard in terms of related installation and site requirements are summarized below, hope customers installation must follow the implementation, such as the failure to GB require the installation of any problems arise, the unit is responsible for installation.
One, fitness equipment and ground-mounted and buried structures shall meet the following requirements (with a larger frame chassis ground except for fitness equipment):
1, column buried fitness equipment, shall be securely fixed to lateral support or the support plate;
2, the installation of fitness equipment soil, in the depth of less than 800 mm above the surface should be tightened coefficient is not less than 0.7 Class Ⅱ hard soil and above ordinary non osteoporotic and non-sandy loam type of geological structure; Otherwise, the soil Equivalent treatment, before installing fitness equipment;
Note: Tightening coefficient is not less than 0.7 Class Ⅱ general hard soil can be excavated and a few spade hard with picks excavation to determine the degree of difficulty. Require excavation and a few spade force excavated soil with picks, can be regarded as fastening coefficient is not less than 0.7 Class Ⅱ ordinary hard soil
3, fitness equipment, buried depth column: When the fitness equipment above the ground when the height ≥ 2000 mm, shall be not less than 500 mm; fitness equipment height above ground ≥ 1000 mm and <2000 mm, it should be not less than 400 mm; fitness equipment height above ground <1000 mm, it should be not less than 300 mm; fitness equipment below the bottom of the column should be not less than 100mm thick concrete supporting layer;
4, each support leg fitness equipment installed concrete pit horizontal dimension shall be not less than 400 mm * 400 mm, without concrete foundation should be disposed of as the next big small shapes;
5, pouring fitness equipment strength of concrete used in the foundation should not be less than C20, and the foundation is not completely solidified before, someone should guardianship;
6, fitness equipment installed, the support legs and the body should be perpendicular to the ground to ensure the installation, vertical tolerance should not exceed 1/100;
7, from the outer edge of fitness equipment foundations 0.5 m wide ground should be hardened, for example: the concrete to harden, tamp the soil after brick paving, etc.; equipment in and around the hardened surface of the ground should not exceed safety fitness equipment installed around ground.
Second, security equipment, fitness equipment and the surrounding environment venues, shall meet the following requirements:
1, fitness equipment from overhead high voltage wires horizontal distance of not less than 3 m;
2, fitness equipment from underground pipes, underground lines the edge of the horizontal distance of not less than 2 m, from all kinds of office buildings, residential and various Church House tubes horizontal distance of not less than 5 m;
3, the use of equipment required to place at night, the equipment within the margin of 2 m, the illuminance should be not less than 15 lx;
4, fitness equipment should stay away from flammable, explosive and toxic and hazardous materials, site fitness should conform to the relevant provisions of the security.
Three, horizontal bar, parallel bars, ladders, swings, etc. or may bounce up and down movement falling from the air movement equipment, the movement should be soft or elastic ground floor buffer, for example: sand layer, rubber floors. For rubber flooring, its floor structure thickness shall not be less than 25 mm; case of bunkers, the sand layer thickness should not be less than 200 mm, and height should be adequate bunkers surrounding envelope boss, boss's edge edges, sharp corners should be set to a radius of not less than 10 mm in radius.
Fourth, exercise stations and sports stations from the edge of the range of human motion shall not be less than 1 m.
Five, fitness equipment design and installation, ensure secure, reliable and vertically, there should be a base member and a supporting member of loosening and shaking phenomenon.

没有评论: